Caltrans crews began rebuilding curb ramps and sidewalks along Tiburon Boulevard the week of September 21. The City of Mill Valley confirmed the start in a notice dated September 24. The project is State Route 131 Capital Preventive Maintenance, and it covers 4.6 miles from Tower Drive in Mill Valley to the roundabout at Main Street, where Tiburon Boulevard turns into Paradise Drive. By the time it's done, the whole corridor will have new pavement, drainage, curb ramps and intersection work. The new bikeways will cover a much shorter stretch. They end at Blackfield Drive. The section inside town limits, from Blackfield to Trestle Glen Boulevard, is assigned to a second phase targeted for 2029. The last public word on the task force meant to plan that phase came in February, when Tiburon's council offered only "tentative interest" in joining it.
So the road through town is being resurfaced before its final curb-to-curb layout inside town limits has been settled.
The Schedule From Now Through 2027
Crews are starting near the US-101 interchange and moving east toward the waterfront. Here's the published sequence:
- Fall 2026: curb ramps and sidewalks. Phase 1 covers 28 curb ramps. Flaggers may run intermittent one-way traffic control Monday through Friday, 7 a.m. to 5 p.m. Some stretches may need pedestrian detours, and Caltrans says some bus stop locations may be affected, without naming which ones.
- Winter: a pause. Caltrans spokesperson Matt O'Donnell told The Ark the agency plans to stop work during the winter months.
- Spring 2027: repaving. According to a Mill Valley Chamber of Commerce notice cited by the Southern Marin Ledger, paving is scheduled overnight, 11 p.m. to 6 a.m.
- Completion: July 2027 or "winter of 2027." O'Donnell gave The Ark July 2027. Caltrans' own project page says the project will be finished "in the winter of 2027."
Mill Valley's notice says Caltrans is working with Marin Transit and the local school district to limit disruption to bus routes. No closure notice for a specific stop has been published yet. Before a morning drive or a run to the ferry, Caltrans QuickMap shows real-time conditions, and the project page posts each new traffic advisory.
Three Stretches, Three Different Outcomes
The whole corridor gets the same pavement and drainage work. The bike and pedestrian improvements change from one segment to the next, and the line between them falls close to the town boundary.
| Stretch | What Phase 1 delivers for bikes and pedestrians |
|---|---|
| Tower Drive to Knoll Road | Class II bike lanes on both sides of the road, including over the Highway 101 overpass |
| Knoll Road to Blackfield Drive | Class IV protected bikeways at the South Knoll and North Knoll approaches. On the inbound side, a temporary two-way Class I multiuse path runs from Strawberry Drive to Blackfield |
| Blackfield Drive to Trestle Glen Boulevard | No new bike lanes. Deferred to Phase 2 |
| Trestle Glen to Main Street | Pavement and intersection modifications |
The Strawberry-to-Blackfield path matters most to the neighborhoods around Greenwood Cove. It connects to the existing Class III route on Greenwood Cove Drive and Greenwood Beach Road. The Ark reports that residents there have long raised concerns about bike traffic and have asked for faster cyclists to be routed out to Tiburon Boulevard. The path is labeled temporary, and a permanent version is planned for Phase 2. The Marin County Bicycle Coalition has described the Strawberry-to-Greenwood Cove link as closing a "persistent sidewalk gap." It has also called the mile and a half between Highway 101 and Blackie's Pasture a long-standing gap in the county's bikeway network.
Under the current plan, cyclists heading toward downtown will have dedicated space as far as Blackfield. From there to Trestle Glen, the road looks the way it does today.
Why the Line Falls at Blackfield
Caltrans originally included bike lanes between Blackfield Drive and Trestle Glen Boulevard. It reversed that decision after the Tiburon Peninsula Traffic Alliance, the Reed Union School District and the City of Belvedere raised concerns about school-bus service. The Traffic Alliance runs the local school-bus program. It said the bus provider, First Student, would not serve four stops if the lanes went in: outbound at Jefferson Drive, and inbound at the 76 gas station, Cecilia Way and Blackie's Pasture.
The details of the four stops became the center of the debate. Bike advocates with WTB-TAM pointed out that the Blackie's Pasture stop sits at the parking lot entrance, beyond where the inbound lanes would end. They said that on August 29 and September 5 of last year they saw the bus skip the inbound Cecilia Way stop. The Ark saw the same route skip it on September 12. At the 76 station, WTB-TAM measured 22 feet between the curb and the travel lane. A standard school bus is 8½ feet wide. That left Jefferson Drive as the one stop with a documented conflict. Advocates proposed deferring only the northern lanes. Caltrans deferred the entire segment.
Tiburon Mayor Holli Thier had supported including the bike lanes. She described the outcome this way:
"We must now prioritize Phase 2, funding and working closely with Caltrans to ensure bike lanes, bus stops and other elements of the plan are done safely with community input."
WTB-TAM Planning Director Matthew Hartzell said his group hopes Phase 2 "will hopefully complete the protected bike lanes all the way to Trestle Glen Boulevard." He also said the group wants to address concerns about bikes and buses at stops, and about left turns from Cecilia Way onto the boulevard.
Phase 2 Has a Target Date but No Public Schedule
In November 2025, Caltrans said funding for Phase 2 would be secured in 2026 and construction was targeted for early 2029. A stakeholder task force would "develop an endorsed scope and configuration for bikeway and transit improvements," and Caltrans hoped it would convene in early 2026. Caltrans, Marin County and Supervisor Stephanie Moulton-Peters were coordinating the choice of a facilitator.
On February 11, the county Department of Public Works sent letters to Tiburon, Belvedere, the Traffic Alliance, Marin Transit, the Transportation Authority of Marin and Caltrans' Bay Area office, asking whether each wanted to take part. The proposed facilitator budget was $100,000 to $150,000. On February 18, the Tiburon Town Council asked how many members each entity would send and how the cost would be divided if Caltrans didn't pay for the whole process. Council minutes record that staff were directed to convey only "tentative interest," with "additional clarification and information" needed "before committing any funds."
Those February reports are the most recent public account of the task force, and they describe a process still settling its membership and budget. Early 2029 remains a target rather than a commitment. Whatever gets built between Blackfield and Trestle Glen, including the permanent version of the Strawberry-to-Blackfield path, depends on that process reaching an endorsed design first.
More Plans for the Same Corridor, on Longer Timelines
Two other studies of this corridor are moving forward, and both have long horizons.
On September 24, the Transportation Authority of Marin unanimously adopted its countywide Mobility Hub Plan. Its Tiburon recommendations include safer pedestrian crossings, more visible bus stops, and wayfinding between bus stops and the ferry. Local approvals and funding are still needed. Councilmember Alice Fredericks described the core issue directly. "People have to get to that mobility center," she told the Marin Independent Journal, citing the difficulty of dock parking and hilly neighborhoods without easy access to bus stops.
Where the boulevard meets Highway 101, TAM is choosing consultants for environmental and preliminary engineering studies of the Tiburon Boulevard and East Blithedale Avenue interchange. The final environmental document is targeted for late 2029. Mill Valley's notice says construction isn't expected before 2033, and construction funding hasn't been secured.
These timelines stack up in order. New curb ramps go in this fall. Fresh pavement goes down overnight next spring. The planning for bike and transit space inside town, the ferry wayfinding and the interchange each run on their own schedules, out to 2029 and 2033. The pavement going down in 2027 is the part of the project with a firm date.
If you own a home along Tiburon Boulevard or in the neighborhoods off Blackfield and Trestle Glen, these timelines affect how you get around and, eventually, how your property shows. Stephanie Pratt follows Phase 2 and the corridor studies closely, and is glad to talk through what they could mean for your plans. Schedule a private consultation whenever it suits you.